NEW QUESTION 40
Match each team member with their RACI role.
Explanation:
Match each team member with their RACI role as follows:
* Project Manager: Primary point of contact; manages overall project and communications
* Assessment Team Lead: Ensures proper assessment execution and validates upgrade sequence plan
* Assessment Team: Communicates upgrade progress and issues to the PM
* Delivery Manager: Transitions requirements and upgrade plan to the upgrade team
* Upgrade Team: Point of contact for internal escalations
* Project Manager: Primary point of contact; manages overall project and communications
* The Project Manager is responsible for overseeing the entire project, coordinating all activities, and serving as the main point of contact for stakeholders.
* Assessment Team Lead: Ensures proper assessment execution and validates upgrade sequence plan
* The Assessment Team Lead oversees the assessment phase, ensuring that the evaluation is thorough and that the upgrade sequence is properly planned and validated.
* Assessment Team: Communicates upgrade progress and issues to the PM
* The Assessment Team members are responsible for executing the assessment tasks and reporting progress and any issues encountered to the Project Manager.
* Delivery Manager: Transitions requirements and upgrade plan to the upgrade team
* The Delivery Manager is responsible for ensuring that all requirements and the upgrade plan are effectively communicated and handed over to the upgrade team for execution.
* Upgrade Team: Point of contact for internal escalations
* The Upgrade Team handles the actual upgrade process and serves as the primary point of contact for any internal escalations that may arise during the upgrade.
References:
* Dell EMC project management and RACI documentation.
* Industry best practices for defining roles and responsibilities in a RACI matrix.