The SAP C_TS412_2021 certification exam is designed for individuals who want to prove their knowledge and skills in SAP S/4HANA Project Systems. This certification is intended for professionals who are involved in managing and implementing SAP projects. The exam measures the candidate’s ability to perform various tasks related to project management, such as planning, monitoring, controlling, and reporting.

 

NO.12 Your customer has created networks with internal activities and generated capacity requirements. Now, they want to analyze the capacity requirements of their project. Which report do you recommend?

 
 
 
 

NO.13 Which organizational structures are required for network activities? Note: There are 3 correct Answers to this question.

 
 
 
 
 

NO.14 In your project. You work with a network and external activities. You have created a purchase requisition. The corresponding purchase order is created as well. Now, you increase the quantity of the external activity. How does the system support this scenario?

 
 
 
 

NO.15 You have created an internally-processed network activity, and assigned a work center and the work.
After saving, you discover that no planned costs are displayed in the cost element report for the activity.
What could be the reason? Note: There are 3 correct Answers to this question.

 
 
 
 
 

NO.16 You are using networks and external activities in your project. The purchase requisition has been created. What is the sequence for the following business transactions and documents?

 
 
 
 

NO.17 Which planning method can prevent further rescheduling of activities?

 
 
 
 

NO.18 Where can you assign the user status profile for WBS elements? Note: There are 3 correct Answers to this question.

 
 
 
 
 

NO.19 You used hierarchical revenue planning to plan revenues for WBS elements manually. The cost element report for planned revenues does not show any revenues at all. What is the reason for this?

 
 
 
 

NO.20 Project Structure
You plan double the work on each internal activity for multiple project. What do you recommend?

 
 
 
 

NO.21 You plan an activity that starts on February 1 and finishes on February 28. For this activity, you want to define a milestone for February 10 which should NOT be changed through scheduling. What do you recommend for milestone definition?

 
 
 
 

NO.22 What are the prerequisites for delivering materials from the project? Note: There are 2 correct answers to this question

 
 
 
 

NO.23 To which object can you assign a factory calendar?

 
 
 
 

NO.24 A component is assigned to a network activity. What are the prerequisites to generate project stock reservations? Note: There are 3 correct answers to this question

 
 
 
 
 

NO.25 A customer needs to analyse the capacity requirements of their network activities. Which reports do you recommend? Note: There are 2 correct Answers to this question.

 
 
 
 

NO.26 What is the reason for assigning billing plans in customer projects?

 
 
 
 

Download Free SAP C-TS412-2021 Real Exam Questions: https://www.braindumpspass.com/SAP/C-TS412-2021-practice-exam-dumps.html

More Posts

Recent Comments
    Categories

    Post: [May 29, 2023] C-TS412-2021 Test Prep Training Practice Exam Questions Practice Tests [Q12-Q26]